Drywall Ceiling Frame (C-line) Installation

  • Determine the height of the ceiling by attaching the panel to the wall according to the height desired for the room.
  • Attach the panel to the ceiling center by 2 holes using expansion bolts with spaces no more than 1.20 meters.
  • Attach the other end to galvanized wire and adjustable spring and connect to a hook that holds the rail (Level adjustment set)
  • Attach the frames with the hook tightly and adjust to the desired level
  • Attach the lower frame perpendicularly with the upper frame by the locking key
  • Specify the gap of the lower frame for 9 mm, gypsum for 40 cm, and 12 mm gypsum for 60 cm.
  • Follow steps 2-5 for the rest of the room and then attach the gypsum board to the frame by always using screws perpendicular to the lower frame.
  • Plaster the joint between the board and screws, cover all gypsum joints by gypsum cloth tape and plaster all joints all for the rest of the room once again.

Remarks :
Hanger equipment can be used instead of the hook depending on the expertise of the contractor.